AE Yates has removed 27 lighting arches, a kiosk and the halfway house from Southport Pier. New British steel goes in on the landward end later this month.

Southport Pier is being taken apart before it is rebuilt. Sefton Council’s contractor has removed 27 of the pier’s lighting arches. New British steel is due to start going in later this month.

The council set out the progress in an update on Tuesday 8 September (Sefton Council). It is the most detailed account yet of what has come off the structure.

The pier has been shut since December 2022. Structural engineers advised closing it after extreme cold that winter made the decay in its decking worse (Sefton Council).

What has been removed so far

AE Yates, the council’s main contractor, has spent recent weeks dismantling. The update lists:

  • 27 lighting arches disconnected and removed
  • a kiosk and the halfway house taken down
  • a third kiosk in the process of being dismantled
  • the existing handrails, tramlines, and mechanical and electrical services taken away

Scaffolding now runs across the landward section, the stretch nearest the promenade, so the timber decking can be lifted. The contractor has also built an access haul road and two large crane pads on the site. Both are there for the next job: installing the new steel.

Steel replacement starts later this month

The council leader, Cllr Marion Atkinson, said the start of steel replacement “later this month will be a particularly significant milestone”.

Dale Cunniffe, AE Yates’ project manager, described the work so far as “enabling works”. He said the firm is “now preparing to begin replacing steelwork on the landward section of the pier”.

Steel is at the heart of the problem. The council’s FAQ blames a refurbishment in 2000. It says that contractor used the wrong screws and the wrong wood, and did not renew the steelwork and fixings correctly (Southport Pier FAQ). Corrosion of the steelwork was found soon after the pier reopened. The council won its case against the contractor, which then went into liquidation.

The same FAQ says severe decay affects more than 25% of the decking boards. Much of it is inside the boards, where it cannot be seen from the surface.

What the £20 million pays for

The money comes from the Government’s Growth Mission Fund. Its panel approved the council’s business case in March (Sefton Council, 20 March 2026). The approved work includes:

  • full replacement of the decking boards and timber joists
  • extensive steelwork repairs and replacements because of corrosion
  • new gates and CCTV
  • a long-term maintenance regime

Listed building consent was already in place. The pier is Grade II listed, stretches 3,600 feet and is the second longest in Britain.

Before the grant was confirmed, the council paid for about £300,000 of early design and survey work by AE Yates itself (Sefton Council, 5 February 2026).

Timeline of the Southport Pier restoration: closed December 2022; listed building consent by January 2025; Government confirms about £20 million on 29 September 2025; AE Yates reappointed for £300,000 of design and survey work on 5 February 2026; business case approved on 20 March 2026; 27 lighting arches, a kiosk and the halfway house removed by 8 September 2026; new British steel on the landward section later in September 2026.
Three and a half years from closure to the first new steel. The council has not yet published a reopening date.

When will the pier reopen?

The latest update does not say. The council has said before how long the job would take once it started:

  • In September 2025 it put the restoration at 12 to 14 months (Sefton Council).
  • In October 2025 it said approximately fourteen months, with work expected to start in early 2026 (Sefton Council).

The funding was not approved until 20 March 2026, later than that early 2026 start. The council has not published a revised programme. We will report a reopening date when it does.

What it means for you

  • The pier stays shut throughout the works. The council’s FAQ says so plainly.
  • The promenade, Marine Lake and Kings Gardens beside it are open. Our guide to things to do in Southport covers what else is.
  • Expect the most activity at the end nearest the shore. That is where the scaffolding, crane pads and first new steel are.

The council says it will keep publishing regular updates. The contractor also gave a longer interview on episode 3 of the council’s MySefton News Podcast.

Sources