Southport Eastern Access phase 2 at Kew Roundabout needs £4.5m more, blamed on ground conditions, utilities and inflation. Full Council decides on 26 November.
The roadworks at Kew Roundabout need an extra £4.5 million because the ground under them is harder to build on than expected. Sefton’s Cabinet agreed on 5 November to ask Full Council to add the money, and councillors vote on it on Thursday 26 November.
The figure is in the council’s November budget update to Cabinet (Sefton Council, Revenue and Capital Budget Update, November 2026). The works themselves carry on: main construction started on 2 November, as planned.
Why the cost went up
The report gives four reasons for the rise in the cost of phase 2 of the Southport Eastern Access scheme:
- ground conditions, and the engineering needed to deal with them
- utilities found below ground
- land acquisition
- inflation
Ground conditions were already a known problem in Meols Park. The council’s scheme page says the stone base for the new footpath and cycle path there is being left to settle for a few months before it is surfaced, because the ground is poor (Sefton Council).
The extra £4.5 million matches what the council calls “the formal contract offer that has been negotiated with the main works contractor”. The council named that contractor as Balfour Beatty when it confirmed the 2 November start (Sefton Council).
Where the money comes from
The money is an external grant rather than council funds. It is being brought forward from a Liverpool City Region transport fund called Transport for the City Regions, which runs from April 2027 to March 2032.
When that programme was set out in March, it gave the next phase of the Eastern Access scheme £11 million. Phase 2, the work at Kew now under way, is paid for by the current City Region Sustainable Transport Settlement, which ends in March 2027.
The report says the Liverpool City Region has already given initial approval to move £4.5 million of the future allocation forward to phase 2. That is done through a change control form, which the council has received.
The report does not say what happens to the later phase if £4.5 million of its £11 million is spent early.
How big the scheme is
The council’s funding page puts the budget for the whole Southport Eastern Access scheme at £19.97 million, from the current transport settlement (Sefton Council). That page was last updated on 9 April and does not mention the rise.
The extra £4.5 million is equal to about 23 per cent of that budget. The November report does not give a new total for the scheme.
What the works involve
Phase 2 rebuilds the eastern way into Southport around Kew (Sefton Council highway proposals):
- Kew Roundabout gets traffic lights and signalised crossings on every arm
- Scarisbrick New Road gets a wider footway and a cycle path along Meols Park
- Foul Lane is opened up to through traffic and widened
- a queuing lane is added past the mini roundabout towards B&Q
The council expects the main works to take about nine months from 2 November, which runs to around August 2027.
What happens next
Cabinet cannot add the money on its own. It voted to “recommend to Council” a supplementary capital estimate of £4.5 million, funded by the city region grant (Sefton Council, Cabinet decisions, 5 November 2026).
Full Council meets at 6.30pm on Thursday 26 November (Sefton Council). The meeting is open to the public.
What it means for you
If you drive in from Ormskirk, Scarisbrick or the retail parks, nothing changes this week. The works carry on under lane narrowing at Kew, and the council still warns of longer journey times.
The cost rise matters for what comes after. The £11 million set aside for the next phase of the scheme is where the extra money is coming from.
For this week’s closures around Kew and on the M58, see our Southport roadworks page.